Why Daytime Demand Matters for Business Solar
Solar output peaks around the middle of the day, which is when most offices, workshops, cold stores and production lines draw their heaviest load. Every kilowatt-hour used on site replaces one bought at your contracted unit rate, while exported surplus usually earns considerably less. The closer the array tracks your demand, the stronger the case for installing it.
For that reason, we design commercial systems from data rather than roof area. Half-hourly consumption records, which many business suppliers can provide, show how load rises and falls across weekdays, weekends and seasons. A two-shift manufacturer, a distribution unit with refrigeration running around the clock and a nursery that closes at six all need very different systems, even on identical roofs.
Sizing for on-site use
Covering every square metre of roof can leave a business exporting a large share of its output on quiet days. We size systems for high self-consumption and treat export as a useful extra. Where evening or weekend demand is significant, battery storage can be modelled alongside the panels to shift surplus into those hours.
Metal Sheet, Flat and Older Industrial Roofs
Profiled metal sheet roofs
Many industrial units, including large parts of estates such as Team Valley, have profiled metal sheet roofs. Rails either clamp to the profile or fix through to the purlins, depending on the sheet type and manufacturer guidance, and the method is confirmed once the sheet condition has been checked. Fragile roof lights are identified and protected before anyone works near them.
Flat roofs on offices and retail units
Membrane, felt and asphalt flat roofs usually suit a ballasted or low-profile frame that avoids puncturing the waterproofing. Rows are angled for generation and spaced to limit shading, with ballast weights and edge distances set as part of the design.
Fibre cement and ageing coverings
Some older industrial buildings have fibre cement sheeting that may contain asbestos. These roofs need specialist assessment, and replacing or overcladding the sheets is often the sensible first step. We flag this at survey stage so it does not surface halfway through a project.
Structural Checks and Three-Phase Supply
A commercial array spreads extra weight over a large area and adds wind uplift at the roof edges. Under Approved Document A, an increase in roof loading of 15% or more counts as a material alteration, so a structural assessment of the roof and its supporting frame is built into the design wherever the loading calls for one.
On the electrical side, most business premises have a three-phase supply, and inverters are specified to balance generation across the phases. At survey we also check the main distribution board, cable routes from roof to plant room and whether the incoming supply can handle the export the system might produce.
G99 Applications to Northern Powergrid
The G98 limit is 16 A per phase, roughly 11 kW on a three-phase supply, and it counts all generation and storage on the premises together. Almost every commercial system sits above that figure, so it falls under G99. That means an application to Northern Powergrid through ENA Connect Direct, and approval before the system is connected. North East Solar Installer prepares and submits the application as part of the project. The typical target for a low-voltage connection offer is 45 working days, and some offers come with export limits or other conditions, so the application goes in as soon as the design is settled.
Planning Solar for Your Premises?
Send the site address, roof type and a year of electricity invoices or half-hourly data, and North East Solar Installer will set out what a survey of your building would cover.
Do Business Premises Need Planning Permission for Solar?
Non-domestic buildings in England have their own permitted development rights for solar, separate from the householder rules that apply to domestic solar panel installation. Planning Portal guidance, reflecting changes made on 27 August 2026, sets out the main conditions:
- On a pitched roof, panels may project no more than 200 mm from the roof slope.
- On a flat roof, equipment may stand no more than 1 m above the roof and must stay at least 1 m from the roof edge.
- Roof-mounted systems generally need prior approval from the local planning authority, which has 56 days to decide and may ask for a glare assessment.
- Systems above 1 MW can proceed through prior approval.
Listed buildings and conservation areas bring further restrictions. The North East Solar Installer team confirms the planning route for your building during design and builds any prior approval period into the programme alongside the G99 timescale.
Leased Buildings and Landlord Consent
Plenty of businesses rent their premises, and a lease does not stop you going solar, but it does add steps. Check the alterations clause and whether the roof is let to you or retained by the landlord. Written landlord consent is normally required, and managing agents, insurers or lenders may also want to review the proposal.
Agree early who will own the equipment, who maintains it and what happens at the end of the lease or on a sale. In multi-tenant buildings, the meter the system feeds determines who benefits from the generation, so that needs settling before the design is final.
Keeping Disruption to Your Operations Low
Most of the work happens on the roof, so trading usually carries on underneath. We agree the programme with you in advance, covering access routes, edge protection or scaffolding, delivery and lifting of materials, and safe separation of work areas from staff, customers and vehicles. The short shutdown needed to connect the inverters to your distribution board is arranged for a time that suits you, so production lines, tills and IT systems are not caught out.
What Your Commercial Solar Quotation Covers
A proposal from North East Solar Installer sets out:
- System capacity in kWp, with a panel layout drawing.
- Panel, inverter and mounting specifications, with manufacturer warranty terms.
- Estimated annual generation and expected on-site use, with the assumptions shown.
- Structural and electrical findings, and any upgrade work required.
- G99 and planning requirements, and the expected programme.
- Access, scaffolding and safety arrangements.
- Itemised costs and clear exclusions.
- Commissioning, monitoring and handover documents.
Because the assumptions are visible, your finance team can test the figures against their own energy forecasts. The solar panel costs page explains what drives the price of a system.
Business Solar Across the North East
Commercial installations are available in Gateshead, Sunderland, Washington, Cramlington and across the wider region. If your premises already have panels that are underperforming, the solar maintenance and repairs service covers inspections and faults. For homes, see domestic solar panels. To get started, send details of your building and energy use.